New tram exit via chaussée de Haecht/Haachtsesteenweg in Haren
Works resume at the end of January 2026
Published on
STIB-MIVB continues to invest in reliable and future-proof public transport. That's why the Haren depot is getting an additional tram exit. This way trams can leave the depot more easily and transport services remain guaranteed. The surrounding public space is also being redeveloped.
News corner
Where and when will the works take place in Haren?
In rue du Planeur/Zweefvliegtuigstraat and rue de l’Aéronef/ Luchtschipstraat, we installed new tram tracks between January and May 2026 and we connected the tram tracks with the ones on avenue Léopold III/ Leopold III laan. On chaussée de Haecht/ Haachtsesteenweg the bike lane next to the tram tracks will be renewed.
Discover here the building permit and the presentation of track Installation.
Renovation of the streets
Once the tracks are installed, rue du Planeur/Zweefvliegtuigstraat and rue de l’Aéronef/Luchtschipstraat are renovated with special attention to the comfort and security of all road users.
Traffic and accessibility
Since Friday evening, 27 February, traffic on chaussée de Haecht / Haachtsesteenweg has returned to two-way circulation.
Since Monday morning, 2 March, rue du Planeur / Zweefvliegtuigstraat has reopened to local traffic via chaussée de Haecht / Haachtsesteenweg.
As of 12 May 2026, traffic on rue de la Fusée / Raketstraat has returned to two-way circulation. The exit towards Bordet remains accessible. Tram track installation works on boulevard Léopold III / Leopold III-laan and rue de la Fusée / Raketstraat have been completed.
From 18 May 2026, rue du Planeur / Zweefvliegtuigstraat and rue de l’Aéronef / Luchtschipstraat will become one-way streets from chaussée de Haecht / Haachtsesteenweg towards rue de la Fusée / Raketstraat. At rue de la Fusée / Raketstraat, traffic will be able to turn both left and right. Public space redevelopment works will start.
Works on chaussée de Haecht/ Haachtsesteenweg are completed, and all lanes have been reopened sinds 31 May 2026.
From May 2026