Works in Rue de l’Étoile/Sterstraat
Works from February 2026 to mid-2027
Published on
Tram works on the STIB-MIVB network at rue de l’Étoile/Sterstraat. Stay updated and plan ahead for traffic and accessibility changes!
What is happening and why?
To maintain service quality and comfort, STIB-MIVB is renewing the tram tracks and upgrading the Keyenbempt stops in rue de l’Étoile/Sterstraat, between rue de Stalle/Stallestraat and rue Fleurbeek/Fleurbeekstraat. But before that, Vivaqua is carrying out utility works.
Discover the Étoile/Ster site plan, the Keyenbempt stop plan and the diversion plan for vehicles over 3.5 tonnes here.
Utility works first
From 16 February to September 2026, Vivaqua is carrying out utility works on the sewer system and individual connections. The works are organised in phases and may affect access and local traffic. The schedule may still change.
Communication for this phase will be handled by Vivaqua. Questions can be addressed to info.chantiers@vivaqua.be or +32 2 518 85 24 (weekdays from 8.30 am to 4.30 pm). Other utility works may also take place during this period.
Tramwerken
Na afloop van de nutswerken start de MIVB met het vervangen van de tramsporen, wat ongeveer vijf maanden zal duren. Aansluitend worden de haltes Keyenbempt opnieuw aangelegd om het comfort en de toegankelijkheid te verbeteren. De definitieve planning hangt af van de voortgang van de werken van Vivaqua. Verdere communicatie volgt later in de wijk.
Want to keep track of the works?
- WhatsApp channel
- Ombuds service: Questions? Contact Lynn Gehot via 0490 67 71 83 or Lynn.Gehot@stib.brussels.
Traffic and accessibility
Tram line 82 remains suspended throughout the works.
From February 2026, bus line 74 towards Clémence Everard will be diverted between Drogenbos and Carrefour Stalle/Kruispunt Stalle via Grand’Route/Grote Baan and rue Prolongée de Stalle/Verlengde Stallestraat. Direction Van Haelen, the bus already follows this route.