Works rue de la Régence/Regentschapsstraat and tram stops Petit Sablon/Kleine Zavel

Updating facilities for an improved and safer mobility

The tram tracks on rue de la Régence/Regentschapsstraat have reached their limit and are due to be replaced. This is part of an ongoing upgrade of the public transport network to provide an ever more reliable and efficient service. The new equipment will also help reduce the vibrations generated by passing trams, thereby improving passenger comfort. The project will cover the entire length of rue de la Régence/Regentschapsstraat, between place Poelaert/Poelaertplein and place Royale/Koningsplein.

Petit Sablon/Kleine Zavel stops

All-new Petit Sablon/Kleine Zavel stops for greater passenger safety and comfort

The total redevelopment of the stops serves three purposes: to improve passenger safety and comfort, and ensure access to trams for people with reduced mobility. Currently, passengers have to cross a traffic lane when getting off the tram. Despite the fact that drivers are not allowed to overtake a stationary tram, this creates significant risks for passengers. The new platforms will be raised and accessible directly from the trams. This will mean no more dangerous crossings, while ensuring access for people with reduced mobility and pushchairs. Cyclists will also benefit from a safer experience thanks to the installation of an off-road cycle lane behind the stops.

A project in tune with the neighbourhood's heritage

The iconic historical setting of rue de la Régence/Regentschapsstraat deserved special attention. The project has been designed to blend harmoniously with the area's heritage. The chosen materials, such as blue stone paving slabs and granite stones, echo the area's visual identity, while meeting modern standards of quality and durability.

All-new Petit Sablon/Kleine Zavel stops for greater passenger safety and comfort

The total redevelopment of the stops serves three purposes: to improve passenger safety and comfort, and ensure access to trams for people with reduced mobility.

Accessibility maintained during the works

The works have been scheduled with two priorities in mind:

  • Limiting the disruption to local residents and users: the works will be carried out in several sections, from place Poelaert/Poelaertplein to place Royale/Koningsplein.
  • Ensuring continued easy access to the Grand Sablon/Grote Zavel:  Traffic (in one or both directions) will be maintained at all times in rue de la Régence/Regentschapsstraat. The street will be open for the Brussels 20km and the National Day celebrations.

You can find all the traffic plans in 'Downloads' (only in french and dutch).

Works schedule

  • Vivaqua will begin on Monday 13 January 2025 and proceed in 7 sections until mid-April 2025.
  • From March to September 2025, STIB-MIVB will replace its tram tracks in 5 sections and redevelop the stops Petit Sablon/Kleine Zavel.

Specific measures required to maintain traffic flow in rue de la Régence/Regentschapsstraat.

These will apply only to the section affected by the works.

  • Pavements will be temporarily narrowed but kept at a minimum width of 2 metres.
  • Parking and stopping will be restricted depending on the phase of the works.
  • One lane of traffic (usually on the even-numbered side) will be closed to all traffic, including for local residents.

Stay informed

  • Website: Focusing on ensuring access to the Grand Sablon/Grote Zavel involves a detailed phasing of the works, with variable impacts. Find out about the various phases of the works and their impact on www.stib-mivb.be/Regence-Regent.
  • Information letters: Delivered to local residents’ letterboxes.
  • Via email: Send “INFO Regence” to Anne-Marie.Eelen@stib.brussels.
  • Via WhatsApp: Send “INFO Regence” + your name to 0490 14 14 30.
  • Direct contact: Anne-Marie.Eelen@stib.brussels or 0800 21 640 for questions or specific issues (moving house, deliveries...).
  • Vivaqua contact: For specific questions about the works carried out by Vivaqua, contact info.chantiers@vivaqua.be or 02 518 85 24.

Public transport

  • Trams 92 and 93 will not be running in rue de la Régence/Regentschapsstraat from 13 January to October 2025.
  • Bus 33 will be locally diverted. Bus 95 will not be affected until May 2025.

For more information: on www.stib-mivb.be, the STIB-MIVB mobile application, Floya, at 02/5638917 or the stops concerned.